Read Recent Journals
Entered By: Paula
Entry Date: 2013-04-11 15:10:07
Subject: Construction Rolls On
Message:
 

The exterior walls on the Community Center are up!

The roof is being constructed by Jose the Welder (much like Bob the Builder)

Repello is being put on over the block.

Floor will be poured in May.

 

As construction rolls along I hope that you are praying with us regarding the what, who, and how of this project. 

Already we see the building can be used as a place to fry the plantain chips, bake the baked goods for the Comunicafe (Celebraccion outreach), hold tutoring and English class, reading room, story time, community meetings, place for local Hondurans to teach pertinent classes, and as a safe place for youth to gather (when we have recreation tables, computers, movie set-up, etc. 

Please pray with us, pray about a way you can be involved.  Will you buy a ping pong table?  Would you send 100 Spanish books?  Do you want to install a projector?  Would you come and paint the walls?  Maybe you want to do story time and craft? 

We thank you for your continuing support!

Paula

Replies to this message
re: Construction Rolls On  by Holly B on Monday April 15, 2013




Read Recent Journals

Other messages by Paula
Lenten season  by Paula on Saturday March 04, 2017
re: Justice  by Paula on Saturday March 04, 2017
A smidge of realization  by Paula on Saturday January 21, 2017
re: Tuesday January 17, 2017  by Paula on Thursday January 19, 2017
Rock on God  by Paula on Thursday January 19, 2017
Tuesday January 17, 2017  by Paula on Tuesday January 17, 2017
Tough one  by Paula on Tuesday November 22, 2016
Prayers for Carlitos  by Paula on Friday November 04, 2016
Christmas opportunity!  by Paula on Sunday October 30, 2016
Saturday October 15, 2016  by Paula on Saturday October 15, 2016

See other journal entries

747